The Contract Holder should be advised to submit an Alterations & Improvement application form for retrospective permission to be considered as per the above process.
If retrospective permission is refused or if the contract holder fails to apply, the Contract Holder may be asked to reinstate the property to its original condition.
If the Contract Holder fails to complete reinstatement works within the agreed timescales or to the required standard, Bron Afon’s Asset Team may make arrangements to complete the repairs/re-instatement and recharge the cost of this to the Contract Holder.
Considerations: A visit may be required to the contract holder following completion of the work to ensure the work complies with both legal and Bron Afon requirements. If this is required, the Contract Holder should be advised to contact us on completion of the works.